How to build a preventive maintenance plan, step by step
From inventory to the first round: how to decide which equipment is in, how often, what gets checked on each visit and how to leave evidence, with a template you can copy.
Updated on · 5 min read · Qribo team
A preventive maintenance plan answers four questions for each unit: what gets checked, how often, how (with which checklist and which measurements) and what remains as evidence. Everything else —the software, the label printer, the calendar— is just how you make sure the plan gets carried out without depending on anyone's memory.
This guide goes from inventory to the first round. It works the same for a hotel, a plant, a building or a company that services several clients.
1. Inventory: which equipment is in
Not everything with a motor deserves preventive maintenance. Start with a list with three columns: unit, location and what happens if it fails.
- Definitely in: anything that stops the operation or puts people at risk (water pumps, boilers, fire detection systems, elevators, air conditioning in critical areas, electrical panels, compressors on a production line).
- In if the manufacturer requires it to keep the warranty.
- Can wait: things that fail without consequences and are cheap to replace.
Give each unit a criticality (low, medium, high, critical). Later it will help you prioritize breakdowns: a failure on a critical unit can't compete with the hallway lamp.
If your list lives in Excel, don't throw it away: it's the basis of your inventory. Almost any software can import it.
2. Frequencies: how often
Three sources, in this order:
- The manufacturer's manual. It almost always gives intervals (running hours, months) and what to check.
- The regulations that apply to you (for example, periodic inspections of fire protection systems or elevators in your country).
- Your own experience: if a unit fails every three months, checking it every six doesn't help.
Typical frequencies as a starting point (adjust them to your reality):
| Equipment | Usual frequency | What's usually checked |
|---|---|---|
| Air conditioning (split, cassette) | Monthly or quarterly | Filters, drain, pressures, supply air temperature, current draw |
| Water pump | Monthly | Noise, vibration, leaks, pressure, amperage |
| Boiler / water heater | Monthly + annual overhaul | Pressure, temperature, burner, safety valves |
| Electrical panel | Quarterly or every six months | Connection tightness, temperature, cleaning, protections |
| Fire detection | Monthly (test) + annual (certification) | Detector and sounder tests, panel battery, logbook |
| Compressor | By running hours | Oil, filters, belts, pressure, leaks |
| Generator | Monthly (start-up) + every six months | No-load start, fuel, battery, oil |
Start with a lower frequency than you think and increase it if failures appear between checks. A plan nobody follows because it's too dense is worse than a modest one that actually gets done.
3. The checklist: how it's checked
Each type of equipment needs its template: the list of points to check on every visit. Rules that make it work in the field:
- Short. Between 8 and 15 points. Past 20, nobody reads it; everything gets ticked green.
- Concrete. "Check filter" is vague; "Filter clean or replaced" can be verified.
- With measurements where they matter. Pressure, temperature, amperage, voltage: a number with its normal range. If it's out of range, it's an alert, not a footnote.
- With required photos on the points that later cause disputes (filter condition, nameplate, repaired leak).
- With a wrap-up: the unit's overall condition and remarks.
Example template for an air conditioner:
| Point | Type | Normal range |
|---|---|---|
| Filter clean or replaced | Yes/No + photo | — |
| Drain clear | Yes/No | — |
| Supply air temperature | Number (°C) | 12–16 |
| Suction pressure | Number (psi) | depends on the refrigerant |
| Compressor current draw | Number (A) | per the nameplate |
| Abnormal noise or vibration | Yes/No | — |
| Remarks | Text | — |
If you use software, measurements with a range let the system open a breakdown on its own when a value goes out of range, and let you see each unit's trend over time.
4. Who and when: the schedule
With equipment, frequencies and templates defined, the plan turns into tasks with dates. Two decisions:
- By unit or by location. A round can cover a whole floor (every unit on level 3) or a single unit. For buildings and hotels, by location is usually more efficient; for critical equipment, by unit.
- Who does it. Assigned to a technician, or open for whoever is on site to take.
This is where the spreadsheet breaks down: someone has to watch the calendar, tell the technician, confirm it was done and record the result. A system generates it on its own and puts it in the technician's daily schedule.
5. Evidence and wrap-up
Every check should leave, at a minimum:
- The completed checklist, with the measurements.
- Photos of what matters (before and after if there was an intervention).
- The signature of whoever receives the work (site manager or client), ideally on the spot.
- A report that reaches the right people without anyone having to put it together afterwards.
Without evidence, preventive maintenance is an act of faith. With evidence, it's a history that protects you with the client, the insurer and the auditor, and tells you which equipment is worth replacing.
6. Review the plan
Every three or six months, look at the history:
- Which units keep failing despite preventive maintenance? Increase the frequency or review the template.
- Which checks never find anything? Maybe you can space them out.
- Which measurements are drifting toward the edge of the range? That's where the next breakdown is.
A template to get started
Copy this table and fill it in with your first 10 or 20 units:
| Unit | Location | Criticality | Frequency | Template | Responsible |
|---|---|---|---|---|---|
| AC-301 | Floor 3, room 301 | Medium | Quarterly | Air conditioning | In-house technician |
| PMP-01 | Pump room | Critical | Monthly | Water pump | In-house technician |
| PNL-GF | Basement, main panel | High | Every six months | Electrical panel | Electrical contractor |
When that table falls short, it's time to move it into a system. In Qribo each row becomes a unit with its QR, the frequency becomes a recurring task that's generated on its own and the template becomes a checklist the technician completes on the phone with photos, measurements and a signature. You can import your Excel file (guide in Spanish) and schedule the first round the same day.